Every reconciled factor, with the quantity and hours it was derived from.
| Scope item | Date | Installed | Hours | Actual /hr | Bid /hr | Factor |
|---|---|---|---|---|---|---|
| Drywall Level 4 board hang — north wing | 2026-08-17 | 47 sheets | 8 | 5.88 | 6.00 | 0.98On rate |
| Drywall Level 5 board hang — north wing | 2026-08-18 | 29 sheets | 8 | 3.63 | 6.00 | 0.60Critical |
| Framing Level 5 metal stud partitions | 2026-08-20 | 210 lin ft | 12 | 17.50 | 18.00 | 0.97On rate |
Factor is actual install rate ÷ bid rate. Below 1.00 is slower than bid. A scope item with hours but no measurable quantity produces no row at all — a gap is shown as a gap, never as a zero.